Latest works to Emergency Village

Last week’s progress to the #BTHEVandCC Emergency Village and Critical Care Scheme build included:

Works to levels 1 and 2, this includes Mechanical and Electrical First Fix and Wiring, Partition Second Fix and Spray Plastering.

In addition to this, work to the Roofing and Plantroom continued and is showing outstanding levels of progress. This included works to the Roof Coverings, Mechanical and Electrical First and Second Fix Install and Roof upstand install to the existing phase 5 plant chiller deck.

Works also continued to the brick installation to the West Elevation.

Pictured below is the Spray plastering on level 1.

Posted in Emergency Village.